Karnataka's PM MITRA textile park finally moves after clearance delays

Karnataka's delayed PM MITRA park in Kalaburagi gains pace: Rs 320 crore sanctioned inside, Rs 390.2 crore outside, with Rs 10,000 crore investment and one lakh jobs targeted.

Cut
November 13, 2026
Sew
3 min
Ticket
TKT-3B9E
PM MITRA Textile Park project finally takes off in Karnataka
PM MITRA Textile Park project finally takes off in KarnatakaTheOtherKev / pixabay

Construction

  1. Karnataka sanctioned Rs 320 crore for first-phase works inside the Kalaburagi PM MITRA park and Rs 390.2 crore outside.

  2. The park targets Rs 10,000 crore of investment and over one lakh direct and indirect jobs on 1,000 acres.

  3. Nine companies signed MoUs worth Rs 1,900 crore at the March 2023 ground-breaking.

  4. Environmental clearance delayed the project by more than nine months; KIADB must deliver its DPR within two weeks.

  5. A 17-km pipeline tender, a 12.9 MLD water supply DPR and a 180 MW power line tender are all in progress.

India's PM MITRA textile park in Kalaburagi, Karnataka, has finally gathered momentum after environmental clearances and land conversion delayed the scheme by more than nine months. The state has sanctioned Rs 320 crore for first-phase works inside the park and Rs 390.2 crore for works outside it, and expects the project to attract Rs 10,000 crore in investment and create over one lakh direct and indirect jobs.

The park sits on 1,000 acres of land belonging to KPCL near Honnakiranagi and Firozabad in Kalaburagi taluk. Planners chose the site because of the cotton grown across Yadgir, Vijayapura, Raichur, Bidar and other parts of the Kalyana Karnataka region. Karnataka's government also frames the project as a way to stabilise the lives of migrant labourers in the region and curb large-scale out-migration.

What infrastructure work is underway?

A barrage across the Bhima river at Naduvinahalli village, built to secure drinking water for the project, is nearing completion, along with road and drainage works outside the park. The tender for a 17-km pipeline from the barrage to the park is currently under scrutiny. The Urban Water Supply Department is preparing a detailed project report (DPR) to supply 12.9 MLD of water from the Nandikur sewage treatment plant. A tender has also been called for a 180 MW power supply line.

Inside the park, the Karnataka Industrial Areas Development Board (KIADB) is preparing the DPR for infrastructure works. Officials directed the board to finish the report within two weeks so development can start once the Union government approves it.

Why did the project fall behind?

The government first planned to develop the park under a public-private partnership model through global tenders, then revised the plan and handed responsibility to KIADB. Raghavendra Hosamani, Deputy Director of the Handlooms and Textiles Department, said: "The land identified for the Textile Project comes under greenfield. Developing infrastructure in this area is challenging because everything must be taken up from scratch, unlike in brownfield land where all facilities are already available."

He added that environmental clearance took more than nine months and that agricultural land had to be converted for industrial use before work could begin.

Who has committed investment?

The government signed memoranda of understanding with nine private companies in cotton processing and textiles at the project's formal ground-breaking in March 2023. Those MoUs carry an expected investment of Rs 1,900 crore. These are signed commitments reported by state officials; the wider Rs 10,000 crore figure remains a project estimate rather than a booked order book.

For cotton suppliers in the region, the park changes the economics of processing. Farmers previously transported their cotton to Gujarat because the region had no ginning mills. New ginning capacity in Yadgir, Raichur and surrounding districts should keep that value-addition local and support higher cotton production.

What pressure does the timeline create?

Industrialists are pressing the state to speed up the works, noting that all six other PM MITRA parks announced by the central government in 2023 have made significant progress. They argue that full implementation of the Kalaburagi park would redraw the region's industrial map by generating employment and reducing migration.

For sourcing teams, the decision the news forces is simple: track the KIADB DPR approval and the barrage-pipeline completion before building Kalaburagi into any capacity plan. Until the Union government clears the internal-works report and water infrastructure is linked, the park remains a commitment on paper with a construction schedule, not yet an alternative to established Tamil Nadu or Gujarat textile clusters.

via apparelviews.com (Source)